CONSTRUCTION UPDATES

Recent and upcoming construction activities are listed below.


Item | Construction Timeline

Crews Mobilize to Site and Prepare Laydown Yard | February 24, 2025 - April 2, 2025

Measures to Control Stormwater and Erosion Install | February 27, 2025 - March 26, 2025

Grubbing Cleared Areas | March 3, 2025 - March 28, 2025

Install Access Roads | March 13, 2025 - March 28, 2025

Grading (Reshaping Land) According to Approved Plans | March 13, 2025 - April 9, 2025

Install Security Fencing | April 7, 2025 - June 2, 2025

Piles (Vertical Metal Poles Panels Attach To) Delivery and Install | April 30, 2025 - September 2, 2025

MV (Medium Voltage) Cable Delivery and Install | May 21, 2025 - August 12, 2025

Collection Substation Install | April 14, 2025 - December 9, 2025

Inverters (Converts DC Power Collected from Panels to AC Power) Delivery and Install | May 8, 2025 - June 3, 2025

Racking (Affixes Solar Panels to Piles) Delivery and Install | May 19, 2025 - October 8, 2025

Modules (Solar Panels) Delivery and Install | June 3, 2025 - November 3, 2025

Commissioning (Testing of Equipment Before Energization) | August 19, 2025 - March 12, 2026

Final Restoration (Finishing touches on landscaping, vegetation, etc.) | September 5, 2025 - March 12, 2026